HDGL Storage Buildings and Hot Strip Mill

WHAT WE DID

Lowering construction costs with minimized steel and fabricator-friendly details.

ABOUT THIS PROJECT

As a member of the CH2M Hill design team, Degenkolb performed structural design of three buildings totaling nearly 1.5 million square feet, and the slab yard crane structure. To facilitate the 4 month fast-track schedule, Degenkolb provided the owner with building foundation loads and a mill order bill of materials prior to selection of the steel fabricators and erector, and then worked closely with the selected fabricators to accommodate multiple process design changes requested by the owner. Degenkolb’s design lowered construction costs by minimizing structural steel material and delivering fabricator-friendly details.

Staff on the Project

INDUSTRY PARTNERS

MSIRobot